Question 39
Q. For existing facilities that are built and have been operating for some time (>20 years), are all sections of the Submission Form mandatory? For example, are the following sections/reports required for an operating hydro facility? - Section 3.3: Site Compliance - Section 3.4.6: Recognition of the project by local authorities - Section 3.4.7: Project Insertion Plan - Section 3.6.2: Environmental impact assessments - Section 3.6.3: Federal environmental assessment procedure - Section 3.6.4: Environmental approval plans - Section 3.10.5: Estimated cost of substation - Section 3.10.8: Letter demonstrating compliance with standards and technical requirements for connection to the Grid. Any guidance on the submission form for existing hydro facilities would be greatly appreciated.
***Réponse en français et anglais ci-après***
A. As indicated in Section 3.6 of the Call for Tenders Document, the bidder must answer all questions and provide all of the required information and documents. If a bidder considers that a question does not apply to its project, the bidder must write “N/A” as a reply and provide a justification.
R. Comme indiqué à l’Article 3.6 du document d’Appel d’offres, le soumissionnaire est tenu de répondre à toutes les questions et fournir toutes les informations et tous les documents demandés. Dans le cas où un soumissionnaire juge qu’une question ne s’applique pas à son projet, le soumissionnaire doit inscrire comme réponse la mention « S/O » et fournir une justification.